Every date that built this house
50 dated milestones from the first deposit in August 2021 to the twelve-month inspection in May 2024.
2021
15 milestonesInitial home deposit paid
Today I paid my initial deposit to Henley to begin my new home. Hooray!
Second deposit
Second deposit paid to Henley
Henley contacted me
Henley contacted me to say they had made a mistake on my quote and needed to charge me an extra $2235
Henley’s soil testing
Henley’s soil testing contractor called me and wanted to book a time at my place the next day. As I was expecting other works to me occurring I moved that to the followin…
Henley’s site survey
Henley’s site survey contractor called me to book a time for next Thursday
Pro-cut on site
Pro-cut on site to remove some trees.
Access granted to Henley Member site
Today I was sent login credentials for Henley’s member site. This is the go-to site for information regarding your build.
Bookings made for Colour
Bookings made for Colour Appointment and Tender Appointment.
Colour Appointment
Colour Appointment with Bridie. The event was held virtually due to COVID lockdowns.
Siting drawings received
Siting drawings received.
Tender appointment
My Tender appointment with Sam P was on this day.
Electrical appointment booked
Electrical appointment booked
Third deposit
Third deposit paid to Henley.
Final drawings
Final drawings received with some enforced modifications put in.
Electrical appointment today
The friendly Jocelyn hosted my Electrical Appointment.on this day.
Read the entry →2022
13 milestonesDemolition completed
Woo Hoo! Demolition works have now been completed. This is a major milestone. The next major milestone is formal finance approval and signing my final contract with Henle…
Read the entry →Cut/cap sewer tie in
Henley will ask that you complete this step prior to formal completion of demolitions works and will not proceed any further until it’s done. You can read about it here
Read the entry →Contract received
The time between demolishing my old home and presenting my contract to build my new home felt like forever. Read about it here.
Read the entry →Contract signed
This was the day I finally signed my building contract. Read more here
Read the entry →Builders insurance received
Receiving the builders insurance is important for a number of reasons, at this stage I needed it for my finance company,
Read the entry →5% Deposit paid to Henley
The final deposit was paid to Henley. From here on, it will be progress payments
Read the entry →Building permit issued
My project required a building permit only, not a planning permit.
Power pit installed
If you are unfortunate enough to be dealing with AusNet, you should set low standards, then you won’t be disappointed. Just hopeless.
Transferred to construction
This was the day my file was internally transferred from Henley admin, to construction. About bloody time.
Construction begins
On site construction finally begins with the site cut/fill and set out. Check photos here
Read the entry →Bored piers completed
The bored piers are needed to stabilize the concrete slab. They are bored (drilled) into the ground, re-enforced, then concreted. There is a photo of them here
Read the entry →Underground power and drains installed
Conduit and wiring from the power pit at the front of the property was laid, As was the storm water and sewer drains. Photos are here.
Read the entry →Concrete slab complete
A major milestone was reached on Thursday August 11th – the concrete slab was successfully poured. Henley invoiced me for the base progress payment before the first concr…
Read the entry →2023
21 milestonesConstruction photos – December 2022
Despite the construction industry winding down for the annual Xmas holiday period, good gains were made in the available time. Construction activities are not expected to
Read the entry →Here’s how Henley responded to my latest building inspection
On November 18, 2022 I had an independent building inspector conduct a Waterproofing/Fix audit of Henley’s work. What follows is a copy of that report, along with some of
Read the entry →Project update – January 2023
Almost all of the construction industry shut up shop for the Xmas break, building works on my site were no different. Henley ceased work for the year around December 20th
Read the entry →How Henley attempts to cover up quality issues.
. Recently I conducted a detailed owner’s inspection of my new home before I headed off for a quick overseas holiday. As you may recall, Henley recently attempted to bloc
Read the entry →Construction photos – January 2023
. Most of Melbourne’s construction industry shut down for the annual Xmas holiday period and my site was affected by that as any. So it should come as no surprise that th
Read the entry →Project completion is close.
In a series of emails it has emerged that my home is nearing completion. A few days ago I was invited to attend a “Pre Handover Walk Through”, which I will attend on Marc
Read the entry →Project update – February 2023
From late January through most of February I was on holiday overseas, which probably explains why this update is late and I’ve been rather quiet on this website. Rest ass
Read the entry →Construction photos – February 2023
For most of February I was MIA while holidaying overseas, for this reason all of this months construction photos were taken late in the month. Completion is close As you
Read the entry →Henley jumps the gun on payment
There is nothing that Henley does faster than emailing off an invoice when they want to get paid. On the day of my concrete slab pour, the base stage invoice arrived in m
Read the entry →Final building inspection report
On March 7, 2023, my Completion Stage building inspection was conducted. As at the date of publication there has been no formal response from Henley, though I did attend
Read the entry →Project update – March 2023
Henley have gone into liquidation… April Fool ! Alright, it was a poor joke… Before I start on the March update I want to touch on the terrible news yesterday that one of
Read the entry →Henley have handed over my new home.
It’s with a great deal of happiness that I can tell you that I’m writing this post while sitting in the lounge room of my new home. After frustratingly slow progress afte
Read the entry →Don’t expect your Henley home to be secure
Handover day is full of excitement. Sure, the site meeting with Henley’s site supervisor is pretty routine, but once you have your keys it’s on with the fun bit – moving
Read the entry →Post handover report – 1 month
Over the coming months I’ll share with you what’s happening in and around my new home. These reports will likely be every 3-6 months and will include any works Henley has
Read the entry →We’ll be back after this short break…
If you think it’s been a little quiet on this website recently, you’d be right. I’ve been overseas for the last month and expect to fly back in a little over a week. Ther
Read the entry →Post handover report – 3 month
Wow, 3 months has flown by. I have spent half of that time travelling overseas and the rest of the time I’ve been making gradual changes inside the house. Recent news rep
Read the entry →Henley left drainage problems
During the construction phase of my home build Australia experienced a La Nina weather event which leads to wetter than usual conditions across Australia. With that in mi
Read the entry →What I love about my Henley home
It’s almost 2 years since I paid my initial deposit to Henley beginning the process of knocking down my old house and rebuilding a brand-new home. Over those 2 years I’ve
Read the entry →Henley really is incompetent.
Since my blog post detailing the drainage issues Henley left me with, I’d planned to add an Agi pipe along the front of my home to assist in evacuating the water that was
Read the entry →Post handover report – 6 months
Time has flown since Henley handed me the keys to my new home. On handover day I was well aware that there was still some works that Henley still needed to complete – tha
Read the entry →Henley: Water flows uphill
It’s been 7 months since handover almost to the day and Henley have finally decided to have a good go at fixing the drainage problems they created. Yesterday morning Henl
Read the entry →2024
1 milestonesHenley 12 month inspection was today
Firstly, yes I know it’s been a while since my last post – I’ve been away from home for a number of months during the last year and when I’m here in Melbourne I’m working
Read the entry →Every milestone links to the entry written at the time, where one exists.