Site cut to handover — the slab, the frame, the delays, and the independent inspections that found what the supervisor missed.

34 entriesJul 2022 – Apr 2023
All entries

Newest first

Search the archive →

Project update – March 2023

Henley have gone into liquidation… April Fool ! Alright, it was a poor joke… Before I start on the March update I want to touch on

Final building inspection report

On March 7, 2023, my Completion Stage building inspection was conducted. As at the date of publication there has been no formal re

Henley jumps the gun on payment

There is nothing that Henley does faster than emailing off an invoice when they want to get paid. On the day of my concrete slab p

Construction photos – February 2023

For most of February I was MIA while holidaying overseas, for this reason all of this months construction photos were taken late i

Project update – February 2023

From late January through most of February I was on holiday overseas, which probably explains why this update is late and I’ve bee

Project completion is close.

In a series of emails it has emerged that my home is nearing completion. A few days ago I was invited to attend a “Pre Handover Wa

Construction photos – January 2023

. Most of Melbourne’s construction industry shut down for the annual Xmas holiday period and my site was affected by that as any.

How Henley attempts to cover up quality issues.

. Recently I conducted a detailed owner’s inspection of my new home before I headed off for a quick overseas holiday. As you may r

Project update – January 2023

Almost all of the construction industry shut up shop for the Xmas break, building works on my site were no different. Henley cease

Here’s how Henley responded to my latest building inspection

On November 18, 2022 I had an independent building inspector conduct a Waterproofing/Fix audit of Henley’s work. What follows is a

Construction photos – December 2022

Despite the construction industry winding down for the annual Xmas holiday period, good gains were made in the available time. Con

Project update – December 2022

Mid last week saw onsite construction activities cease for the Xmas holiday period, however, satisfactory progress was still achie

What’s not included in Henley’s base price?

Few would be surprised to learn that when a builder advertises the price of their home designs online or in the media there will d

Construction photos – November 2022

Cupboards, vanities and benches have been installed in all rooms. A flurry of activity took place inside the house in the first co

Project update – November 2022

November was a relatively busy month onsite with the brickwork beginning in the second half of the month, that should be completed

Henley attempted to block my access to site 

Today I visited my project to inspect some quality issues and snap the final photos for this month’s construction photos but the v

Construction photos – October 2022

There’s been a lot going on in my life in recent weeks so I’m a little late with the construction photos this month. As you’ll see

Independent building inspection – here’s what they found.

** Up front disclaimer** Posting this report is not posted to in any way defame any person at all. Every effort has been made to r

Project Update – October 2022

After a somewhat disappointing month in September, onsite activities ramped up in October with most of the work being completed in

Why I employed an Independent Building Inspector

It costs a pile of money to build a new home, and there’s plenty of risks to be considered well before you decide on a builder. So

Henley Member Site

Unnoticed by most visitors to the Henley.com.au website, there is portion of the site which is not accessible by the general publi

Henley – Pre construction report card

It was the end of August 2021 when I paid my initial deposit to begin the process of building with Henley. From that time until mi

Construction photos – September 2022

Disappointingly, construction activities slowed down significantly from the bumper months of July and August. Two of my recent blo

Delay Letter from Henley

If you’ve read my project up date for September, you’ll recall that I received a Delay Letter from Henley which caught me by surpr

Project update – September 2022

Following on from my bullish project update for August, September has seen a disappointing slowdown in onsite activity. Early in t

Contract variation #1

The digital ink on my contract had only been dry around a week before I got my first inkling that I was about to get an unpleasant

Construction photos – August 2022

August has seen activities on site ramp up significantly, as you will see by August construction photos. To be brief, earthworks w

Why I chose Henley. An honest answer.

A few months after I started this website, I got an email asking me why I chose Henley over other builders. At the time I emailed

Project update – August 2022

Construction has been under way for a little over 6 weeks now and I’m pleased to report that Henley are doing a great job of progr

Financing your new home

There’s so much to consider when deciding whether to build a home on your land, or simply purchase a ready made home. Things get m

Website crash

Some of you may have noticed that this website has looked a little different for a few days. The truth is one of the plugins which

Construction photos – July 2022

It’s been a long journey. From signing on with Henley at the end of August 2021, to reaching the construction phase of my build. O

I finally got my building contract

was the day I put pen to paper to commence the early stages of building with Henley. It’s been a long road to get there, but towar

Back in action

Regular visitors to the site will have noticed it’s been a while since my last blog post, sorry for the delay. The last few months