We built a Carmelle 25. This is everything that happened.
Fifty-eight entries and 50 dated milestones — from the first deposit to the twelve-month inspection. The delays, the invoices, the defects, and the parts that turned out beautifully.
Not a brochure. A record.
Henley is one of Australia's largest home builders. In 2021 I knocked down an old house and rebuilt on the same block. Everything that followed is documented here in the order it happened — including the parts a sales office would rather you didn't read.
Three parts of one build

Choosing, quoting, signing
Tender, colour appointment, electrical plan, contract and the costs that only appear after you have committed.

Slab to handover
Site cut to handover — the slab, the frame, the delays, and the independent inspections that found what the supervisor missed.

Living in it
Month one, three, six and twelve — what settled, what failed, and what Henley came back to fix.
Every date that built this house
50 milestones, in order, with the date each one happened. Filter by phase or jump to a year.
2021
15 milestonesInitial home deposit paid
Today I paid my initial deposit to Henley to begin my new home. Hooray!
Second deposit
Second deposit paid to Henley
Henley contacted me
Henley contacted me to say they had made a mistake on my quote and needed to charge me an extra $2235
Henley’s soil testing
Henley’s soil testing contractor called me and wanted to book a time at my place the next day. As I was expecting other works to me occurring I moved that to the followin…
Henley’s site survey
Henley’s site survey contractor called me to book a time for next Thursday
Pro-cut on site
Pro-cut on site to remove some trees.
Access granted to Henley Member site
Today I was sent login credentials for Henley’s member site. This is the go-to site for information regarding your build.
The timeline continues through handover in April 2023 and the twelve-month inspection in May 2024.
Open the full timeline →