A build diary · Melbourne, 2021–2024

We built a Carmelle 25. This is everything that happened.

Fifty-eight entries and 50 dated milestones — from the first deposit to the twelve-month inspection. The delays, the invoices, the defects, and the parts that turned out beautifully.

Henley Carmelle 25Eastport facade 58 entries50 milestones

Not a brochure. A record.

Henley is one of Australia's largest home builders. In 2021 I knocked down an old house and rebuilt on the same block. Everything that followed is documented here in the order it happened — including the parts a sales office would rather you didn't read.

58Entries
50Milestones
8Inspections
The spine of the site

Every date that built this house

50 milestones, in order, with the date each one happened. Filter by phase or jump to a year.

2021

15 milestones
August 312021
Milestone

Initial home deposit paid

Today I paid my initial deposit to Henley to begin my new home. Hooray!

September 42021
Milestone

Second deposit

Second deposit paid to Henley

September 92021
Milestone

Henley contacted me

Henley contacted me to say they had made a mistake on my quote and needed to charge me an extra $2235

September 142021
Milestone

Henley’s soil testing

Henley’s soil testing contractor called me and wanted to book a time at my place the next day. As I was expecting other works to me occurring I moved that to the followin…

September 162021
Milestone

Henley’s site survey

Henley’s site survey contractor called me to book a time for next Thursday

September 172021
Milestone

Pro-cut on site

Pro-cut on site to remove some trees.

September 182021
Milestone

Access granted to Henley Member site

Today I was sent login credentials for Henley’s member site. This is the go-to site for information regarding your build.

The timeline continues through handover in April 2023 and the twelve-month inspection in May 2024.